Sector:
  • Offshore

Expertise:
  • Load-in & load-out

  • Heavy transport

Benefits:
  • Optimized schedule

Location:
  • Brazil

2,200t moves engineered in a short timeframe, protecting the project schedule.

Offshore construction specialists Estaleiros do Brasil Ltda. (EBR) needed the load-out of seven modules to be engineered, planned, and executed in the space of just a few weeks.

These modules were being built in Brazil and destined for FPSO integrations abroad; the challenge was to have the modules in active production as soon as possible.

The modules – some weighing up to 2,200t each and over 30m by 18m in size – were to be transferred from the quay to a waiting ship. Phase one of the project would transfer the first four such modules, and phase two the remaining three.module transport for petchem.jpg

The work was not straightforward, however. A challenge presented itself during the first phase, as there were limited feasible jacking points available underneath the module. These are strengthened areas, built into a module’s design, that allow it to be lifted from underneath by large jacking systems.

As there was no sufficient time to reinforce the structure of each module so that they could be jacked down using other points, an alternative solution had to be found. It came through the innovative use of standard lifting equipment.

Hydraulic trailers used for transport projects have the ability to raise and lower mechanically, so it was decided that each module would be lowered sequentially, using the hydraulic course of the trailers rather than traditional jacking equipment. In turn, each module was weighed, jacked down to the correct grillage height, then loaded out onto the ship within a precise timeframe.artistic impression of heavy module transport.jpg

Despite the novel approach, this methodology allowed the first four modules to be loaded-out in just twelve days instead of the allotted 15.

Phase two of the operation, which included the three final modules, was successfully completed a few months later. During this phase, only the weighing and load-out were required. To complete this scope, Mammoet's team mobilized the same 96 axle lines of PST/THP trailers as previously used, a large selection of weighing and auxiliary equipment, and it could mobilize staff from every corner of the Americas to ensure the job was done on time.

During phase two, the largest module measured over 29.9m (around 98,000 ft) long and 37.488m (122.9 ft) tall. Again, each module’s weight aligned with expectations, at around 2,200t each.

Mammoet Project Manager, Alvaro Campos, explains, “One of Mammoet’s greatest challenges was the mobilization time since we were asked to deliver with very short notice and the required equipment was in various locations across Brazil. We managed to get everything to the site on time thanks to the hard work of a very professional crew and we pulled out a safe execution which was praised many times by our final clients and brought them much relief.”